Determined

APN 065-0118-027Zone R-2

demo-snapshot · fetched Jun 10, 2026

Completeness determinationnot started
Decision51 of 60 days left

City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.

Status

  1. Draft
  2. Submitted
  3. In review
  4. Revision requested
  5. Determined (current)

Completeness determination

15of 15 days remaining

Not started.

Gov. Code §66317 (SB 543, eff. 1-1-2026) — ≤ 15 business days from receipt

Clock starts at submission receipt.

Decision

51of 60 days remaining

Stopped — 9 used.

Gov. Code §66317 — ≤ 60 days from completed application (ministerial, no hearing)

Day-zero is acceptance-as-complete, not first upload.

City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.

Latest automated check

Approve

All 63 checks passed with no failures, flags, or items requiring further review. The application meets all applicable requirements as evaluated, and the computed recommendation is to approve. No outstanding issues were identified for the reviewer's attention.

This is the AI agent's recommendation, not a decision — a named human signs every determination.

Determination

Approve
All automated checks passed with citations. Approved for issuance subject to standard conditions. (Demo determination.)

Signed by Maria Chen, Senior Plan Check Engineer (demo) on May 17, 2026