Skip to content

4521 38th Avenue, Sacramento, CA 95824

In review

APN 021-0153-008Zone R-1

demo-snapshot · fetched Jun 10, 2026

Completeness determination14 of 15 days left
Decision58 of 60 days left

City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.

Review & submit

The same completeness check the city would run at intake, run live before you submit — so a "Submittal Incomplete" is structurally impossible.

Completeness manifest

This application is in review — the snapshot is frozen. Track it on the status tab.

Fee estimate

Informational only — recomputed live from your form values. No payment happens here.

  • Building permit fee CDD-0419 rev. 2026-06-05 Table A; research/permitting-laws-sacramento.md §8

    $1,732.95
  • Building plan review CDD-0419 rev. 2026-06-05 Table B; research/permitting-laws-sacramento.md §8

    42% of the building permit fee

    $727.84
  • Fire Dept admin fee CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $173.00
  • Fire Dept inspection CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $0.11/sf, stated minimum $288.00

    $288.00
  • Fire Dept plan review CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $255.00
  • Planning inspection CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $468.00
  • Planning review CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $234.00
  • Public Works review CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $205 deposit + hourly; only the deposit appears in CDD-0419's printed examples. Hourly charges beyond the deposit are not estimable from this instrument — display as '$205 deposit + hourly'.

    $205.00 deposit + hourly
  • Utilities (DOU) fee CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    $205 deposit + hourly; only the deposit appears in CDD-0419's printed examples. Hourly charges beyond the deposit are not estimable from this instrument — display as '$205 deposit + hourly'.

    $205.00 deposit + hourly
  • C&D recycling processing CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    city's printed example at 1200 sf

    $81.98
  • City business operation tax CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8; docs/04-builder-portal-spec.md §Screen 6

    city's printed example at 1200 sf

    $81.98
  • Construction excise tax CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    city's printed example at 1200 sf

    $945.60
  • General plan fee CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    city's printed example at 1200 sf

    $533.00
  • Green building fee (state) CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8

    city's printed example at 1200 sf

    $9.00
  • Residential construction tax (3+ bdrm rate) CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8, §10 item 14

    $315.00
  • Strong motion fee (state) CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8; docs/04-builder-portal-spec.md §Screen 6 legend

    city's printed example at 1200 sf

    $26.64
  • Technology fee CDD-0419 rev. 2026-06-05; research/permitting-laws-sacramento.md §8, §10 item 14

    city's printed example at 1200 sf

    $203.39
  • Park development impact fee CDD-0419 rev. 2026-06-05; Gov. Code § 66311.5(c)(1); research/permitting-laws-sacramento.md §8 boundary note; docs/04-builder-portal-spec.md §Screen 6 SB 13 threshold

    city's printed example at 1200 sf

    $4,164.00
  • SAFCA flood DIF CDD-0419 rev. 2026-06-05; Gov. Code § 66311.5(c)(1); research/permitting-laws-sacramento.md §8 boundary note; docs/04-builder-portal-spec.md §Screen 6 SB 13 threshold

    city's printed example at 1200 sf

    $2,520.00
  • STA mitigation fee (+2% admin) CDD-0419 rev. 2026-06-05; Gov. Code § 66311.5(c)(1); research/permitting-laws-sacramento.md §8 boundary note; docs/04-builder-portal-spec.md §Screen 6 SB 13 threshold

    city's printed example at 1200 sf

    $1,381.68
  • School impact fee

    Paid at the school district office — never computed by the portal, never rendered as $0 (docs/04 §Screen 6 acceptance criterion 4)
  • Regional sanitation / sewer development

    Check with County — never computed by the portal, never rendered as $0 (docs/04 §Screen 6 acceptance criterion 4)

Estimated total (city-collected items)

$14,551.06
Estimate, not a quote — informational only, computed from CDD-0419 rev 06-05-2026. The city sells a formal estimate for $164 via CDD-0278 to [email protected] (CDD-0423 p.2). City valuation basis: $170.8/sf (CDD-0419 "Accessory Dwelling Unit (ADU) Fee Estimate (New Construction)" rev 2026-06-05). No payment happens in this product — estimation only. The city sells a formal estimate for $164 via CDD-0278 ([email protected]).
Greenlight by YIMBY Labs