1316 Weller Way, Sacramento, CA 95818

In review

APN 021-0143-027Zone R-1

demo-snapshot · fetched Jun 10, 2026

Completeness determination14 of 15 days left
Decision20 of 60 days left

City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.

Status

  1. Draft
  2. Submitted
  3. In review (current)
  4. Revision requested
  5. Determined

Completeness determination

14of 15 days remaining

Stopped — 1 used.

Gov. Code §66317 (SB 543, eff. 1-1-2026) — ≤ 15 business days from receipt

Clock starts at submission receipt.

Decision

20of 60 days remaining

Running — 40 used.

Gov. Code §66317 — ≤ 60 days from completed application (ministerial, no hearing)

Day-zero is acceptance-as-complete, not first upload.

City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.

Latest automated check

Request revision

This application is recommended for revision. Of 65 checks run, 64 passed and 1 failed. The single failure involves a rear setback that falls short of the minimum required distance for an ADU located within 60 feet of the front property line. The applicant will need to revise the plans to bring the rear setback into compliance before the application can move forward.

This is the AI agent's recommendation, not a decision — a named human signs every determination.