1316 Weller Way, Sacramento, CA 95818
In reviewAPN 021-0143-027Zone R-1
demo-snapshot · fetched Jun 10, 2026
City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.
Status
- Draft
- Submitted
- In review (current)
- Revision requested
- Determined
Completeness determination
14of 15 days remaining
Stopped — 1 used.
Gov. Code §66317 (SB 543, eff. 1-1-2026) — ≤ 15 business days from receipt
Clock starts at submission receipt.
Decision
20of 60 days remaining
Running — 40 used.
Gov. Code §66317 — ≤ 60 days from completed application (ministerial, no hearing)
Day-zero is acceptance-as-complete, not first upload.
City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.
Latest automated check
This application is recommended for revision. Of 65 checks run, 64 passed and 1 failed. The single failure involves a rear setback that falls short of the minimum required distance for an ADU located within 60 feet of the front property line. The applicant will need to revise the plans to bring the rear setback into compliance before the application can move forward.
This is the AI agent's recommendation, not a decision — a named human signs every determination.