Application review
1316 Weller Way, Sacramento, CA 95818
In reviewAPN 021-0143-027 · app_18125582-f810-4f1b-a441-fd5267b8460b · submitted May 3, 2026 · accepted complete May 3, 2026
City cycle targets for residential new buildings: 20/15/5 working days for cycles 1/2/3 (CDD-0294, rev 03-04-2026) — an expectation, not a promise.
Parcel
- APN
- 021-0143-027
- Zone
- R-1
- Lot area
- 6,000 sq ft
- Overlays
- none
- GIS source
- demo-snapshot · fetched Jun 10, 2026
Application
- Standards path
- A — Local option (≤1,200 sf combined)
- Permit holder
- Property owner
- Valuation
- $112,000
- New sq ft (living)
- 640 (640 first / 0 second)
- Garage sq ft
- 0
- Stories
- 1
- Description of work
- Construct a new detached 640 sf one-story accessory dwelling unit (studio / 1 bath) beside the existing single-family home; all-electric, rooftop PV.
Documents
- tran-cdd0104-address-request.pdfcdd0104 · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- address_request.completeyesfrom cdd01040.97
- tran-CYC1-APP-cdd0200.pdfcdd0200_rendered · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- package.app_size_mb9.60from cdd0200_rendered0.97
- package.export_naming_compliantyesfrom cdd0200_rendered0.97
- package.bookmarks_compliantyesfrom cdd0200_rendered0.97
- document.pdf_restrictions_compliantyesfrom cdd0200_rendered0.97
- tran-cdd0220-owner-builder-wet-signed.pdfcdd0220 · v1 · uploaded May 3, 2026Download
- Readings · source · confidence
- signature.wet_signedyesfrom cdd02200.97
- acknowledgments.initialed_count12from cdd02200.97
- tran-final-certification-wet-signed.pdffinal_certification_signed · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- signature.wet_signedyesfrom final_certification_signed0.97
- signature.date2026-06-02from final_certification_signed0.97
- tran-owner-builder-declaration-wet-signed.pdfowner_builder_declaration_signed · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- signature.wet_signedyesfrom owner_builder_declaration_signed0.97
- signature.date2026-06-02from owner_builder_declaration_signed0.97
- tran-adu-plan-set.pdfplan_set · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- cover_sheet.address1316 Weller Way, Sacramento, CA 95818from plan_set0.97
- cover_sheet.sheet_indexyesfrom plan_set0.97
- cover_sheet.work_descriptionConstruct a new detached 640 sf one-story accessory dwelling unit (studio / 1 bath) beside the existing single-family home; all-electric, rooftop PV.from plan_set0.97
- cover_sheet.description_of_workConstruct a new detached 640 sf one-story accessory dwelling unit (studio / 1 bath) beside the existing single-family home; all-electric, rooftop PV.from plan_set0.97
- cover_sheet.occupancyR-3from plan_set0.97
- cover_sheet.construction_typeV-Bfrom plan_set0.97
- cover_sheet.sprinklersnofrom plan_set0.97
- cover_sheet.sprinklers_primarynofrom plan_set0.97
- cover_sheet.toilet_countsprimary dwelling: 2 WC; ADU: 1 WCfrom plan_set0.97
- cover_sheet.building_typeall_electricfrom plan_set0.97
- cover_sheet.designer_declarationyesfrom plan_set0.97
- cover_sheet.codes_declaration2025 Title 24 with City of Sacramento amendments (ORD 2025-0031; City Code §15.04.050)from plan_set0.97
- cover_sheet.code_cycle_declaration2025 Title 24 with City of Sacramento amendments (ORD 2025-0031; City Code §15.04.050)from plan_set0.97
- site_plan.utility_connection_pointsyesfrom plan_set0.97
- site_plan.abandoned_septic_notenone on parcelfrom plan_set0.97
- site_plan.setbacks_dimensionedyesfrom plan_set0.97
- site_plan.north_arrowyesfrom plan_set0.97
- site_plan.easements_driveways_drainageyesfrom plan_set0.97
- site_plan.sewer_line_details4-in ABS, 2% slope, tie-in at existing lateralfrom plan_set0.97
- site_plan.side_setback_ft5from plan_set0.97
- site_plan.rear_setback_ft2.50from plan_set0.97
- site_plan.front_setback_ft22from plan_set0.97
- site_plan.dist_to_front_line42from plan_set0.97
- site_plan.separation_primary_ft7.50from plan_set0.97
- site_plan.adu_sqft640from plan_set0.97
- site_plan.adu_footprint_sqft640from plan_set0.97
- site_plan.fire_separation_ft10from plan_set0.97
- site_plan.utility_equipment_screenedyesfrom plan_set0.97
- floor_plan.room_usesyesfrom plan_set0.97
- floor_plan.dimensionsyesfrom plan_set0.97
- floor_plan.window_door_sizes_typesyesfrom plan_set0.97
- floor_plan.ceiling_heightyesfrom plan_set0.97
- floor_plan.ceiling_height_ft8from plan_set0.97
- floor_plan.entrance_faces_roadway_or_open_spaceyesfrom plan_set0.97
- elevations.views_nsewyesfrom plan_set0.97
- elevations.height_ft14from plan_set0.97
- elevations.blank_wall_area_sqft120from plan_set0.97
- elevations.mechanical_equipment_concealedyesfrom plan_set0.97
- sections.longitudinalyesfrom plan_set0.97
- sections.transverseyesfrom plan_set0.97
- structural_plans.foundation_footing_detailsyesfrom plan_set0.97
- structural_plans.roof_ceiling_framingyesfrom plan_set0.97
- structural_plans.floor_framingyesfrom plan_set0.97
- structural_plans.braced_shear_wall_plansyesfrom plan_set0.97
- structural_plans.connection_detailsyesfrom plan_set0.97
- electrical_plan.panel_locations_amperage_busbaryesfrom plan_set0.97
- electrical_plan.switch_receptacle_lighting_scaledyesfrom plan_set0.97
- electrical_plan.meter_count1from plan_set0.97
- title24_report.certificates_of_complianceyesfrom plan_set0.97
- title24_report.code_cycle2025from plan_set0.97
- title24_report.climate_zone12from plan_set0.97
- calgreen_checklist.cdd0183yesfrom plan_set0.97
- pv_plans.module_layoutyesfrom plan_set0.97
- pv_plans.one_line_diagramyesfrom plan_set0.97
- pv_plans.spec_sheetsyesfrom plan_set0.97
- pv_plans.cec_labelsyesfrom plan_set0.97
- pv_plans.attachment_detailsyesfrom plan_set0.97
- pv_plans.smud_confirmation_letteryesfrom plan_set0.97
- plan_set.vector_contentyesfrom plan_set0.97
- plan_set.sheet_size_scale_compliantyesfrom plan_set0.97
- package.plans_size_mb42.70from plan_set0.97
- site_plan.lot_coverage_pct29.80from plan_set0.97
- site_plan.has_balconynofrom plan_set0.97
- site_plan.fencing_in_scopenofrom plan_set0.97
- site_plan.adu_in_front_setbacknofrom plan_set0.97
- tran-cdd0312-checklist.pdfsubmittal_checklist_copy · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- checklist.formCDD-0312 rev 01-21-2025from submittal_checklist_copy0.97
- tran-workers-comp-wet-signed.pdfworkers_comp_signed · v1 · uploaded May 2, 2026Download
- Readings · source · confidence
- signature.wet_signedyesfrom workers_comp_signed0.97
- signature.date2026-06-02from workers_comp_signed0.97
Agent recommendation
request revision
Request revisionThis application is recommended for revision. Of 65 checks run, 64 passed and 1 failed. The single failure involves a rear setback that falls short of the minimum required distance for an ADU located within 60 feet of the front property line. The applicant will need to revise the plans to bring the rear setback into compliance before the application can move forward.
pipeline-v1 · rules sacramento-adu-v1 · claude-sonnet-4-6 · started May 3, 2026, 2:26 AM · finished May 3, 2026, 2:26 AM
Determination
Your judgment, your signature
The recommendation is a draft (request-revision) — nothing is decided until you sign.
Prefilled from the agent narrative with citations — edit freely before signing.
Enter your reviewer name to sign — every determination is attributed.
Documentary
completeness — decided deterministicallyObjective
measured against code values — decided deterministicallyJudgment
never auto-decided — flagged for your reviewNo judgment checks applied to this application.